Several new businesses and renovations are underway or coming to the Tomball and Magnolia areas. The following projects have been filed since Dec. 1 through the Texas Department of Licensing and Regulation. The following information may be subject to change.

1. Jack in the Box: 9065 FM 2920, Tomball

Type of work: new construction

Timeline: Feb. 7-May 9

Estimated cost: $850,000


Scope: construction of a fast-food restaurant

2. Office building: 11003 Northpointe Blvd., Tomball

Type of work: new construction

Timeline: Dec. 1, 2021-Dec. 1, 2022


Estimated cost: $600,000

Scope: new single-story wood-framed office building

3. Lovett Grand Parkway 249: Grand Parkway, Tomball

Type of work: new construction


Timeline: Feb. 1, 2022-Feb. 1, 2023

Estimated cost: $45.5 million

Scope: one-story shell building intended for future office and warehouse

4. Spring Creek Greenway Phase V: Burroughs Park, 9738 Hufsmith Road, Tomball


Type of work: new construction

Timeline: March 1-Sept. 30

Estimated cost: $345,000

Scope: 12-foot hike and bike trail


5. Hotworx Studio: 10226 FM 1488, Ste. 300, Magnolia

Type of work: renovation/alteration

Timeline: Feb. 15-May 31

Estimated cost: $150,000

Scope: gym space with sauna booths in Magnolia Shoppes

6. Buffalo Wild Wings GO: 6209 FM 1488, Magnolia

Type of work: new construction

Timeline: Jan. 12-March 16

Estimated cost: $600,000

Scope: tenant build-out of existing space

7. Beauty Salon: 7214 FM 1488, Ste. 105, Magnolia

Type of work: renovation/alteration

Timeline: Oct. 21, 2021-Jan. 31, 2022

Estimated cost: $170,000

Scope: lease space build-out in the Tuscan Village Plaza

8. Westlock Business Park Building 1: 11606 Westlock Drive, Tomball

Type of work: new construction

Timeline: Jan. 15-June 15

Estimated cost: $913,000

Scope: new office building

9. Lone Star College-Creekside Dental Lab: 8747 W. New Harmony Trail, Tomball

Type of work: renovation/alteration

Timeline: March 15-May 23

Estimated cost: $75,000

Scope: interior renovation to create new dental lab area

10. Westlock Business Park Building 2: 11606 Westlock Drive, Tomball

Type of work: new construction

Timeline: Jan. 3-May 31

Estimated cost: $710,000

Scope: new office building

11. Proposed convenience store and future lease space: 9210 FM 2920, Tomball

Type of work: new construction

Timeline: March 1-Sept. 1

Estimated cost: $1.85 million

Scope: proposed convenience store with lease spaces

12. Littlefield Brothers Concrete office: 1310 S. Persimmon St., Tomball

Type of work: new construction

Timeline: Feb. 1-Oct. 7

Estimated cost: $1.5 million

Scope: new single-story office building and warehouse building

13. Ron Investment Properties, LLC/Remax Integrity: 23327 Kuykendahl Road, Tomball

Type of work: new construction

Timeline: Jan. 1-Oct. 31

Estimated cost: $998,000

Scope: single-story building

14. Legacy Preparatory Christian Academy: 9768 Research Forest Drive, Magnolia

Type of work: additions to existing building

Timeline: Dec. 20, 2021-Dec. 21, 2022

Estimated cost: $6.5 million

Scope: two-story school building addition with a half-court gym connected to the existing school building with a bridge