Kuykendahl Road turn lane construction
Contracting company Teamwork will start work in January to add a right-turn lane from northbound Kuykendahl Road onto eastbound Research Forest Drive as well as extending the left-turn lane from northbound Kuykendahl Road onto westbound Research Forest Drive. Work was pushed back from a projected December start due to weather.
Timeline: December-TBD
Cost: $212,224
Funding source: Montgomery County Precinct 3
Grogans Mill Road and Research Forest Drive turn lane construction
Turn lane improvements at Research Forest Drive and Grogans Mill Road were slated to begin in December but delayed due to inclement weather. The project will extend the westbound acceleration lane from southbound Grogans Mill to westbound Research Forest, said engineer John Bleyl of Bleyl Engineering. Improvements will also be performed at westbound Research Forest to northbound Grogans Mill, and utility conflicts at that site were resolved in late December, Bleyl said. Design work for the project is complete, he said.
Timeline: December-TBD
Cost: $240,000
Funding sources: Montgomery County Precinct 2