A project to widen Kuykendahl Road from two to four lanes from Lake Woodlands to Research Forest drives is underway. A new bridge will be constructed over Bear Branch to accommodate the northbound lanes with a shoulder as well as a walkway, and the existing two lanes will become southbound lanes.
As of late October, the contractor had poured the bridge deck over Bear Branch and had completed more than 70% of concrete pavement, according to Precinct 3.
Timeline: January 2021-early 2022
Cost: $3.57 million