Transportation update: $3.57M Kuykendahl Road widening is last project from road bond

Kuykendahl Drive widening begins in early 2021. (Ben Thompson/Community Impact Newspaper)
Kuykendahl Drive widening begins in early 2021. (Ben Thompson/Community Impact Newspaper)

Kuykendahl Drive widening begins in early 2021. (Ben Thompson/Community Impact Newspaper)

The final project from the 2015 road bond for Montgomery County Precinct 3 will widen Kuykendahl Road from two to four lanes from Lake Woodlands Drive to Research Forest Drive, according to Precinct 3 officials. A new bridge will also be constructed over Bear Branch to accommodate the northbound lanes, while the existing two lanes will become southbound lanes.
Timeline: early 2021-early 2022


Cost: $3.57 million


Funding source: Montgomery County Precinct 3

By Vanessa Holt
A resident of the Houston area since 2011, Vanessa began working in community journalism in her home state of New Jersey in 1996. She joined Community Impact Newspaper in 2016 as a reporter for the Spring/Klein edition and became editor of that paper in March 2017 and editor of The Woodlands edition in January 2019.