As executive director of the Grand Parkway Association, David Gornet has been advocating for the construction of the 180-mile loop for 16 years. He became executive director for the association in 2001. Prior to that he worked as a planning and construction consultant. Before his work with the GPA, Gornet worked for 18 years as director of transportation and planning with a consulting firm in Houston. He holds bachelor’s and master’s degrees in civil engineering and is a registered professional engineer in Texas. Gornet said the best thing about being involved in the Grand Parkway construction is the ability to lessen travel time for drivers so they can spend more time with their families.



How long did it take Grand Parkway to get started locally in Harris and Montgomery counties?


Environmental studies were started in 1999, and designs were approved in 2009 for Harris County and in 2010 for Montgomery County. In 2012 the design was passed to [the Texas Department of Transportation] in both counties, and construction began in 2013.



What is the estimated cost and end date for construction on the Grand Parkway?


The estimated cost of construction is $1.2 billion, plus the cost of the land. We’re estimating a finishing date sometime in the latter part of 2015.



What is the noise abatement plan for segment F-1? What are some of the criteria by which those sound barriers are constructed?


Only one subdivision, Fairfield, will have noise walls. The rest of the neighborhoods were far enough away to not need one. There are federal guidelines on whether sound barriers are warranted. Just because there are noise walls doesn’t mean that the noise will go away, and just because traffic is heard doesn’t mean you need a sound barrier. The noise has to be above a certain level, one that is determined by these guidelines, in order to receive a sound barrier.



Which communities or areas around Segment F-2 and Segment G have received sound walls?


Those that are needed in the F-2 section are neighborhoods such as Three Lakes, Glen Loch Forest, Lakes of Avalon, Sugar Berry, Mossy Oaks and Forest North. Segment G has three areas where sound barriers will be installed. Spring Trails, Parks Run and Creekside will all have noise walls. This segment, along with segments F-1 and F-2, should be finished with construction later on this year.



Although the parkway will be located south of The Woodlands and Conroe area, will it still affect traffic in those areas?


It’ll definitely change traffic patterns there, and I see that as a positive impact. That area will also not have any sound barriers and won’t be affected by the noise of the parkway since it’s north of the road. But the parkway will take some traffic from the area and offer quicker trips on the highway rather than taking local roads and having longer travel times.



With the ExxonMobil campus and Springwoods Village development well underway and other projects on the horizon, can we expect more development along the Grand Parkway at major connectors, such as I-45, Hwy. 249, Hwy. 290 and Hwy. 59?


We can certainly expect more development in the area surrounding the Grand Parkway. The [portion of the] parkway that was built 20 years ago that connects Katy to Sugar Land has seen significant growth in its surrounding area. There have been more choices to get places, faster travel times, and the parkway has improved transportation. We’re hoping to see a similar repeat with the Grand Parkway [segments that are] being built now.



What is the biggest effect the Grand Parkway will have on The Woodlands and surrounding areas?


It’s an opportunity for all of Montgomery County to grow and have better choices on where they work, live and shop. This county is a great place to live. I look forward to getting construction finished.



What feedback have you heard concerning the Grand Parkway?


During planning stages there were some concerns because people didn’t understand exactly how it would work. There was some anxiety about that and the type of impact it would have on people’s houses. But we told them to look at the Segment 20-D parkway that was built and the influence in that corridor and how the housing values had not gone down and growth in the area could be seen. So now that the road is currently being built, people are asking when it’ll be finished and can’t wait to use it.



MOST RECENT

Snow covers I-45 in Houston during a winter storm that hit Texas the night of Feb. 14. (Shawn Arrajj/Community Impact Newspaper)
Legislators probe energy officials over power failures, lack of preparation heading into winter storm

The Texas Legislature held hearings Feb. 25 with energy companies including Oncor Electric Delivery and the Electric Reliability Council of Texas in response to last week’s historic winter storm, which left millions of Texans without electricity for days.

The Woodlands Township board of directors met Feb. 24 to discuss items including winter storm recovery and a financial report. (Screenshot via The Woodlands Township)
The Woodlands officials criticize county officials over CARES Act funds management; commissioner fires back

The Woodlands Township board of directors criticized Montgomery County's methods of allocating federal coronavirus aid at the board's Feb. 24 meeting, calling the $244,000 the township received a "slap in the face."

Keith Luechtefeld spoke with Community Impact Newspaper about some of the short-term and long-term repercussions of the storm as well as some of the reasons why so many homes saw burst pipes during the freezing weather. (Community Impact staff)
Q&A: Greater Houston Builders Association President Keith Luechtefeld discusses power, plumbing, frozen pipes after Winter Storm Uri

Keith Luechtefeld spoke with Community Impact Newspaper about some of the short-term and long-term repercussions of the storm as well as some of the reasons why so many homes saw burst pipes during the freezing weather.

Harris County ESD No. 11 commissioners met for a meeting Feb. 25. (Courtesy Cypress Creek EMS)
Harris County ESD No. 11 begins construction process on new facility

District offiicials have said they hope Phase 1 of construction will be complete by August.

Winter Storm Uri led to closures across the Greater Houston area during the third week of February. (Courtesy Metropolitan Transit Authority of Harris County)
‘It’s been a rough year for us’: Expert explains economic effects of winter storm, ongoing pandemic in Houston region

“It's been a rough year for us economically; it's been a rough year for us public health wise. It's just been a rough year for us psychologically—first the coronavirus and then the freeze," said Patrick Jankowski, senior vice president of research with the Greater Houston Partnership.

Gracie Barra The Woodlands relocated to a new training center on Richards Road earlier this year. (Courtesy Gracie Barra The Woodlands)
New cosmetic services, amnMMA gym: 5 recent business updates in The Woodlands and northern Spring

Several businesses have recently opened in or relocated into The Woodlands area.

In addition to produce, Theiss Farms offers grass-fed beef. The family’s herd of cattle grazes in a pasture near the intersection of Spring Cypress and Stuebner Airline roads. (Hannah Zedaker/Community Impact Newspaper)
Theiss Farms Market owner on winter storm: 'I knew everything was going to die, and it did'

Nothing could have prepared local farmers for last week's winter storm, Theiss Farms Market co-owner Dwayne Theiss said.

The $560 million central processor, which is part of the new Mickey Leland International Terminal, will replace the parking garage for terminals D and E. (Courtesy Houston Airport System)
Parking garage at George Bush Intercontinental Airport to be demolished to make way for new Mickey Leland International Terminal

The international central processor, which is part of the new Mickey Leland International Terminal, will replace the parking garage for terminals D and E.

As many as 31 stores across nine states will be shuttered as Fry's Electronics shuts down due to market changes and the pandemic. (Courtesy Qygen, Wikimedia Commons)
Fry's Electronics calls it quits after nearly 36 years in business

As many as 31 stores across nine states will be shuttered as Fry's Electronics shuts down due to market changes and the pandemic.

A lone runner jogs on a snow-covered road in Austin. Transportation projects across the city were briefly paused due to Winter Storm Uri. (Jack Flagler/Community Impact Newspaper)
ERCOT: Texas power system was less than 5 minutes from collapse during winter storm

ERCOT's CEO offered details into what led to the massive blackouts that left millions of Texans in the cold last week.

Emerging technology and alternative energy sectors could help ease the blow of an oil and gas industry downturn in Houston caused by the COVID-19 pandemic, a Houston-area economist said. (Courtesy Visit Houston)
Greater Houston area could see economic relief from pandemic around mid-2021, economist says

Emerging technology and alternative-energy sectors could help ease the blow of the downturn in Houston's oil and gas industry caused by the COVID-19 pandemic.

Most of the electric grid in Texas is managed by the Electric Reliability Council of Texas, which is not linked to other national interconnected systems. (Courtesy Electric Reliability Council of Texas)
Harris County to begin exploring alternatives to Texas power grid at Feb. 26 meeting

Following the winter storm-induced statewide power outages last week that left thousands of Harris County residents without heat amid freezing temperatures, the Harris County Commissioners Court will begin exploring what it would take for Harris County to leave the state's power grid at its Feb. 26 meeting.