On March 18, the Conroe ISD board of trustees received updates regarding progress on campus construction and improvements planned as part of the district’s $1.9 billion 2023 bond, which officials said are proceeding on schedule.

What's happening

Here are some of the projects underway in the district.

Conroe High School
  • Project: The school is making improvements to its campus to accommodate student growth.
  • Update: A new front entrance has been completed, said Easy Foster, executive director of planning and construction for the district.
  • Location: 3200 W. Davis St., Conroe
  • Timeline: completion in 2026
Rob Eissler Elementary School
  • Project: The new elementary school funded by the 2023 bond will have a 950 student capacity and serve The Woodlands High School feeder zone.
  • Update: The inside is being painted, windows are being inserted and drywall is being installed, Foster said.
  • Location: 14000 Old Conroe Road, Conroe
  • Timeline: March 2024-August 2025
Mittie J. Campbell Elementary School
  • Project: The new elementary school will have a 950 student capacity in the Oak Ridge and Caney Creek high school feeder zones.
  • Update: Construction is completed with outer brickwork, Foster said.
  • Location: 15895 Stonecrest Drive, Conroe
  • Timeline: March 2024-August 2025
New Conroe High School feeder Intermediate Flex No. 26
  • Project: The new intermediate school will serve fifth and sixth grade students in the Conroe High School feeder.
  • Update: Work has begun on the site after approval the previous month, Foster said.
  • Location: FM 1314 and Crighton Road, Conroe
  • Timeline: March-August 2026
New Grand Oaks feeder Elementary Flex No. 27
  • Project: The new intermediate school will serve fifth and sixth grade students in the Grand Oaks High School feeder.
  • Update: Work has begun on the site, Foster said.
  • Location: 5175 Woodson's Spring Drive, Spring
  • Timeline: March-August 2026
Grand Oaks seventh-ninth grade campus
  • Project: The new school will serve seventh, eighth and ninth grades in the Grand Oaks High School feeder zone.
  • Update: The concrete slab is almost complete and the parking lot is done, Foster said.
  • Location: 28075 Woodson’s Grand Drive, Spring
  • Timeline: March 2024-August 2026
Timber Mill High School
  • Project: The high school will create a new feeder with students from Conroe and Caney Creek high schools.
  • Update: The crew is working on the underground utilities to install the concrete slab foundation, Foster said.
  • Location: Loop 336 next to Stockton Junior High School
  • Timeline: November 2024-August 2027
Timber Mill Junior High School
  • Project: Timber Mill High School will create a new feeder with students from Conroe and Caney Creek high schools.
  • Update: Clearing effort has begun for the road and the junior high school building, Foster said.
  • Location: FM 1314 south of Loop 336
  • Timeline: December 2024-August 2027
Timber Mill ninth grade campus
  • Project: Timber Mill High School will create a new feeder with students from Conroe and Caney Creek high schools.
  • Update: Clearing effort has begun for the campus, Foster said.
  • Location: FM 1485 at Hwy. 242
  • Timeline: December 2024-August 2027