Here are some of the projects underway in the district.
Conroe High School
- Project: The school is making improvements to its campus to accommodate student growth.
- Update: A new front entrance has been completed, said Easy Foster, executive director of planning and construction for the district.
- Location: 3200 W. Davis St., Conroe
- Timeline: completion in 2026
- Project: The new elementary school funded by the 2023 bond will have a 950 student capacity and serve The Woodlands High School feeder zone.
- Update: The inside is being painted, windows are being inserted and drywall is being installed, Foster said.
- Location: 14000 Old Conroe Road, Conroe
- Timeline: March 2024-August 2025
- Project: The new elementary school will have a 950 student capacity in the Oak Ridge and Caney Creek high school feeder zones.
- Update: Construction is completed with outer brickwork, Foster said.
- Location: 15895 Stonecrest Drive, Conroe
- Timeline: March 2024-August 2025
- Project: The new intermediate school will serve fifth and sixth grade students in the Conroe High School feeder.
- Update: Work has begun on the site after approval the previous month, Foster said.
- Location: FM 1314 and Crighton Road, Conroe
- Timeline: March-August 2026
- Project: The new intermediate school will serve fifth and sixth grade students in the Grand Oaks High School feeder.
- Update: Work has begun on the site, Foster said.
- Location: 5175 Woodson's Spring Drive, Spring
- Timeline: March-August 2026
- Project: The new school will serve seventh, eighth and ninth grades in the Grand Oaks High School feeder zone.
- Update: The concrete slab is almost complete and the parking lot is done, Foster said.
- Location: 28075 Woodson’s Grand Drive, Spring
- Timeline: March 2024-August 2026
- Project: The high school will create a new feeder with students from Conroe and Caney Creek high schools.
- Update: The crew is working on the underground utilities to install the concrete slab foundation, Foster said.
- Location: Loop 336 next to Stockton Junior High School
- Timeline: November 2024-August 2027
- Project: Timber Mill High School will create a new feeder with students from Conroe and Caney Creek high schools.
- Update: Clearing effort has begun for the road and the junior high school building, Foster said.
- Location: FM 1314 south of Loop 336
- Timeline: December 2024-August 2027
- Project: Timber Mill High School will create a new feeder with students from Conroe and Caney Creek high schools.
- Update: Clearing effort has begun for the campus, Foster said.
- Location: FM 1485 at Hwy. 242
- Timeline: December 2024-August 2027