The following commercial projects have been registered recently in the area with the Texas Department of Licensing and Regulation. All information, including costs and timelines, is subject to change.
1. Impact Church of The Woodlands
- Location: 5401 Shadowbend Place, The Woodlands
- Type of work: new construction
- Timeline: September 2024-September 2025
- Estimated cost: $6.4 million
- Location: 4840 W. Panther Creek Drive, Ste. 107, Spring
- Type of work: renovation/alteration
- Timeline: Aug. 15-Oct. 31
- Estimated cost: $300,000
- Location: 25336 Richards Road, Spring
- Type of work: new construction
- Timeline: September 2024-August 2025
- Estimated cost: $8 million
- Location: 17225 I-45 S., The Woodlands
- Type of work: renovation/alteration
- Timeline: October 2024-December 2025
- Estimated cost: $87 million