On Aug. 6 the Harris County Flood Control District released the final list of bond projects for
the $2.5 billion flood prevention bond election that will go before voters Aug. 25.
Early voting runs from Aug. 8-21. Find early voting locations near you
here.
The final list of bond projects includes suggestions made by residents in a series of meetings held throughout the summer to solicit community feedback on the projects.
Here are some highlights of the list provided by HCFCD. See the full list
here.
Spring Creek watershed:
Right-of-way acquisition and general drainage improvements: $10M
Investigate general drainage improvements along Spring Creek: $500,000
Right-of-way acquisition and floodplain preservation: $50M
Federal grant-funded volunteer home buyouts: $75,000 local match
Planning, right of way acquisition, design and construction of
a reservoir along Spring Creek: $12.5M local match
Subdivision drainage improvements: $1.6M local match
Storm repairs: $90,000 local match
San Jacinto River Watershed
San Jacinto Watershed study: $625,000 local match