Four years after Hurricane Harvey, 10 of 25 drainage efforts from Fort Bend County’s 2019 flood bond are unfunded or on pause. However, five of the six projects affecting the Sugar Land and Missouri City areas are moving forward.
Flooding was still front of mind for many Fort Bend County residents when voters approved the county’s $83 million flood bond in November 2019—two years after Harvey devastated the area in August 2017.
Mark Vogler, the Fort Bend County Drainage District general manager and chief engineer, said most of the paused projects are due to a lack of supplemental funding. He described the county’s bids for grants to use with bond money as “wishful thinking.”
“These projects were just so, so massive in cost that the county was saying, ‘We don’t have the funds right now to do this bigger project—but let’s see if we can get a grant, and if we can get a grant, maybe we can move the project forward by percentage of it,’” Vogler said.












