Read about some of the latest updates on transportation projects in the Sugar Land-Missouri City area. This list is not comprehensive.
1. Cartwright Road reconstruction
Project: The project will reconstruct the road during the first phase, with the second phase to add additional lanes.
Update: Design of the first phase is nearing completion, with Phase 2 design underway.
- Timeline: second quarter of 2026-second quarter of 2027 (Phase 1); second quarter of 2027-fourth quarter of 2027 (Phase 2)
- Cost: $7.2 million
- Funding source: city of Missouri City and Fort Bend County
2. Henry Watts and Knight Road roundabout
Project: The project will replace the intersection with a roundabout due to increased traffic.
Update: At a March 2 meeting, Missouri City City Council approved a design agreement with LJA Engineering.
- Timeline: construction slated to begin in first quarter of 2027
- Cost: $314,668 (design)
- Funding source: city of Missouri City
3. Sugar Land On-Demand renewal
Project: The on-demand program to give residents an affordable transportation option in a limited service area.
Update: At a March 3 meeting, Sugar Land City Council approved the renewal of its microtransit provider.
- Timeline: N/A
- Cost: $1.74 million
- Funding sources: Houston-Galveston Area Council and Fort Bend County bond