This project to extend the existing bridge over the Union Pacific Railroad tracks and Oyster Creek to connect to Stadium Drive in Sugar Land is 70 percent complete. Construction on the bridge deck has begun on the project. Roadway paving and the access road has been installed, and all utility installation has been completed, including water lines and sewers. Timeline: February 2017-March 2018 Cost: $11.5 million Funding source: Imperial Redevelopment District