Transportation Updates

  Transportation Updates Hwy. 90 widening[/caption]

1. Hwy. 90 widening

The Texas Department of Transportation is widening Hwy. 90 in Sugar Land from Hwy. 6 to the Grand Parkway. The road will be widened from four lanes to six lanes across. Durwood Greene Construction is the contractor for the project. As of Aug. 11, the project was 35 percent complete.

Timeline: March-October 2016 Cost:  $10.1 million Funding sources: TxDOT

2. LJ Parkway lowering

Fort Bend County and Levee Improvement District No. 19 are lowering LJ Parkway in Sugar Land from University Boulevard to Hagerson Road. The road has a visibility issue for drivers turning from LJ Parkway onto Hagerson Road. The issue is due to a former levee that was not removed. The intersection did not meet state requirements for an all-way stop or traffic signal, which was originally requested by residents. The project is being contracted through LID 19 with the county contributing funds. LID 19 is managing the project. Construction started in July and is expected to last 90 days.

Timeline: July-October 2016 Cost: $300,000 Funding Sources: LID No. 19, Fort Bend County

Transportation Updates Gregory Boulevard[/caption]

3. Gregory Boulevard

Pavement reconstruction is progressing along the roadway from Fondren Road to McLain Boulevard, and the city of Missouri City is contributing $3.3 million to the project. The contractor is currently finishing underground utilities and working on reconstructing the eastbound lanes. Roadway construction is scheduled to end in the spring of 2017.

Timeline: March 2016-May 2017 Cost: $4.4 million Funding sources: city of Missouri City, Harris County Water Control and Improvement Utility District-Fondren Road

4. Turtle Creek Drive

Work is complete for replacing water lines and moving and replacing the road surface on Turtle Creek Drive from Hilton Head to Mission Valley drives. The city of Missouri City conducted a final walk-through inspection in early August. The city spent approximately 15 months on construction.

Timeline: May 2015-August 2016 Cost: $2.2 million Funding sources: city of Missouri City

Transportation Updates Grand Parkway Segment C-1[/caption]

5. Grand Parkway Segment C-1

Construction of the first portion of Grand Parkway Segment C is expected to be completed this fall. Segment C-1 is a three-quarter-mile feeder road of three southbound lanes, which will serve as an expansion of Crabb River Road. Along with Segment C-1, Crabb River Road’s existing lanes will be northbound. The Grand Parkway is a planned 180-mile scenic highway surrounding the Greater Houston area, and Segment C is a 26-mile portion planned to span from Hwy. 59 in the north to Hwy. 288 in the south. All of Segment C is expected to take until 2025 to complete. Paving on the new lanes of Crabb River Road will begin in the next few weeks.  The work at the Sansbury Boulevard intersection will be complete in September, and new traffic signals will be installed in October.

Timeline: March-November 2016 Cost: $5.6 million Funding sources: Fort Bend County Grand Parkway Toll Authority