Several parks projects are underway in the Katy and Fulshear area, which are set to be completed in 2026 and beyond.

The projects will bring a variety of new and enhanced elements across the area including Fort Bend County’s first all-abilities park. This list is not comprehensive.

Galaxy All Abilities Park

Project: The first county-funded all abilities park will offer space-themed elements including sensory walls, interactive play equipment and tactile elements.
  • Timeline: May 2025-February 2026
  • Cost: $1.27 million
  • Funding source: Fort Bend County parks bond
  • 1515 Stadium Drive, Sugar Land
Cullinan Park Phase 3

Project: The park’s third phase will bring a Learn, Explore, and Play, or L.E.A.P., area that could feature a public pavilion, wetlands, boardwalks and a tree house.


Update: Design for the project is 60% complete.
  • Timeline: March 2025-spring 2026 (design); TBD (construction)
  • Cost: $2.5-$3.1 million (construction)
  • Funding source: Cullinan Park Conservancy fundraising
  • 12414 Hwy 6, Sugar Land
Freedom Tree Park

Project: The project includes an open lawn, public art, a playground, picnic pavilions, restrooms, walking paths, parking and a trail connection to Community Park.

Update: Construction is approximately 75% complete.
  • Timeline: March 2024-March 2026
  • Cost: $4.5 million
  • Funding sources: Missouri City 2021 bond and Texas Parks & Wildlife Department Local Parks Grant
  • 4219 Freedom Tree Drive, Missouri City
Sta-Mo Park

Project: The project includes the construction of multi-purpose sports fields and courts, a multi-wheeled pump track, shade areas, multi-purpose trails, a playground and the installation of native landscaping.


Update: The project is 25% through the design phase.
  • Timeline: Construction expected to begin this summer.
  • Cost: $14 million
  • Funding sources: Missouri City 2021 bond, Fort Bend County parks bond and Texas Parks & Wildlife Department Local Parks Grant
  • 1917 Moore Road, Missouri City
Bicentennial Park

Project: The project adds a new playground, picnic tables, improves lighting and landscaping, and construction of a sidewalk along Woodvale Drive.

Update: Playground, lighting and shade are complete with fencing and landscaping set to finish in spring 2026.
  • Timeline: March 2025-March 2026
  • Cost: $500,000
  • Funding source: Missouri City 2021 bond
  • 2130 Adams St., Missouri City