Curious as to what new businesses and renovations are underway or coming to Sugar Land and Missouri City? The following projects have been filed in the last two weeks through the Texas Department of Licensing and Regulation. The following information may be subject to change.

1. Grand Parkway Medical Office Building: 6424 E. Riverpark Drive, Sugar Land

Type of work: new construction

Timeline: May 2, 2022- May 2, 2023

Estimated cost: $8.3 million


2. Ultra Lash: 16230 City Walk, Sugar Land

Type of work: renovation/alteration

Timeline: May 18-Nov. 18

Estimated cost: $250,000


3. Baby's & Kid's 1st: 2268 Lone Star Drive, Sugar Land

Type of work: renovation/alteration

Timeline: May 5-Aug. 6

Estimated cost: $79,500


4. Greatwood Pickleball: 8802 Greatwood Parkway, Sugar Land

Type of work: new construction

Timeline: April 15-June 1

Estimated cost: $73,350


5. Thomas Plaza: ​​2710 FM 1092, Missouri City

Type of work: new construction

Timeline: April 4-Aug. 8

Estimated cost: $1.050 million