1. Zapvor By Thai Spice: 13517 University Blvd., Ste. 300, Sugar Land
Type of work: new construction
Timeline: March 15-June 15
Estimated cost: $75,000
2. Petco: 10427 Hwy. 6, Missouri City
Type of work: new construction
Timeline: Sept. 1, 2022-Feb. 1, 2023
Estimated cost: $900,000
3. Burlington: 10650 N. Northridge Drive, Missouri City
Type of work: new construction
Timeline: Sept. 1, 2022-Feb. 1, 2023
Estimated cost: $1.5 million
4. Sun Auto: 9060 Hwy. 6, Missouri City
Type of work: new construction
Timeline: Jan. 1-June 30
Estimated cost: $1.33 million
5. Ross: 10435 Hwy. 6, Missouri City
Type of work: new construction
Timeline: Sept. 1, 2022-Feb. 1, 2023
Estimated cost: $1.04 million