Transportation updates

 

Turtle Creek Drive Turtle Creek Drive[/caption]

1. Turtle Creek Drive

The project to replace water lines and remove and replace the road surface on Turtle Creek Drive from Hilton Head to Mission Valley drives in Missouri City was expected to be finished in July. The contractor completed the paving portion of the project, and finished sidewalk and sod for a final walk-through by early August. Alternate lane closures were in effect throughout the duration of the project.

Timeline: May 2015-August 2016 Cost: $2.2 million Funding source: city of Missouri City

2. Gregory Boulevard

Conrad Construction Co. is conducting pavement reconstruction along the roadway from Fondren Road to McLain Boulevard in Missouri City, and the city is contributing $3.3 million to the project. The subgrade was prepared for new pavement in mid-July. Roadway construction is scheduled to begin in June 2016 and be completed by May 2017.

Timeline: March 2016-May 2017 Cost: $4.4 million Funding sources: city of Missouri City, Harris County Water Control and Improvement Utility District-Fondren Road

Street rehabilitation Street rehabilitation[/caption]

3. Street rehabilitation

Street rehabilitation work is mostly complete along Wagon Trail Drive, Sage Brush Lane and Commonwealth Boulevard in Sugar Land. Street closures were conducted during the pavement rehabilitation of outside lanes and inlets. The project is part of a citywide pavement rehabilitation program, which budgeted $1.52 million for fiscal year 2015-16 and will cost an estimated $10.1 million by 2020, according to the city’s Capital Improvement Program.

A. Road closures were conducted for Wagon Trail Drive on June 30. B. Road closures were conducted for Sage Brush Lane on June 30. C. Commonwealth Boulevard closures from Austin Parkway to the roundabout at LJ Parkway lasted from June 28 until mid-July.

Timeline: June-July 2016 Cost: $1.52 million (fiscal year 2015-16) Funding source: city of Sugar Land

4. Austin Parkway improvements

Reconstruction of Lakefield Boulevard in the Lakes of Austin Park area of Sugar Land is completed, and the road is open.  Some additional sodding is needed for the improvements that were made near Austin Parkway. Reconstruction was done to 2,803 linear feet of 8-inch concrete pavement along the road from Hwy. 6 to Commonwealth Boulevard. In addition, 3,000 linear feet of 12-inch water line was replaced. A completion walk-through was conducted in July and work is on track to be finished in August.

Timeline: March 2015-August 2016 Cost: $3.4 million Funding source: city of Sugar Land

LJ Parkway extension LJ Parkway extension[/caption]

5. LJ Parkway extension

Work on the LJ Parkway connection to Commonwealth Boulevard in Sugar Land is completed, and the road opened in mid-July. Riverstone Development led the project to provide a direct route to their property via a single-lane roundabout on Commonwealth Boulevard. The roundabout is located near Palm Royale Boulevard. Construction also included a four-lane, curb-and-gutter roadway from just north of University Boulevard to just south of Commonwealth Boulevard.

Timeline: July 2015-July 2016 Cost: $2.4 million Funding source: Riverstone Development