Curious as to what new businesses and renovations are underway or coming to Sugar Land and Missouri City? The following projects have been filed in the last month through the Texas Department of Licensing and Regulation. The following information may be subject to change.

1. Frogs, Snails, and Fairy Tales: 300 Promenade Way, Ste. 160, Sugar Land

Type of work: renovation/alteration

Timeline: Aug. 15, 2022-Feb. 15, 2023


Estimated cost: $157,500

2. Cannaphoria: 400 Promenade Way, Ste. 1400, Sugar Land

Type of work: renovation/alteration

Timeline: Aug. 15, 2022-March 15, 2023


Estimated cost: $97,500

3. Pet Supplies Plus: 350 Promenade Way, Sugar Land

Type of work: renovation/alteration

Timeline: Sept. 12-Dec. 2


Estimated cost: $750,000

4. Prince Center: 445 Julie Rivers Drive, Sugar Land

Type of work: new construction

Timeline: March 1, 2023-Dec. 31, 2023


Estimated cost: $4.5 million

5. Spice Bazaar Grocery & Kitchen One Stop Shop Halal Meat: 18717 University Blvd., Ste. 155, Sugar Land

Type of work: renovation/alteration

Timeline: Oct. 30, 2022-Jan. 31, 2023


Estimated cost: $100,000

6. Removery: 15293 Southwest Freeway, Sugar Land

Type of work: renovation/alteration

Timeline: Aug. 30-Nov. 15

Estimated cost: $220,000

7. Sharp Floors: 7022 Hwy. 6, Ste. 600, Missouri City

Type of work: renovation/alteration

Timeline: Aug. 15, 2022-March 15, 2023

Estimated cost: $153,750

8. Floors For Living: 8911 S. Sam Houston Pkwy. W., Ste. 100, Missouri City

Type of work: renovation/alteration

Timeline: Aug. 1-Sept. 1

Estimated cost: $85,000

9. Sky Periodontists: 5422 Hwy. 6, Ste. 101, Missouri City

Type of work: renovation/alteration

Timeline: Sept. 30-Dec. 31

Estimated cost: $303,000

10. Sienna Maintenance Facility: 200 Waters Lake Blvd., Ste. 916, Missouri City

Type of work: new construction

Timeline: Aug. 15, 2022-Feb. 15, 2023

Estimated cost: $1.3 million