Here's the latest information on four transportation projects in the Spring and Klein area. This list is not comprehensive.

Upcoming projects

Birnam Wood Boulevard, Segment 2
  • Project: Birnam Wood Boulevard will be expanded from two lanes to a four-lane concrete boulevard with storm sewer and sidewalk between south of Otto Road to Cypresswood Drive.
  • Update: This project is in the design phase.
  • Timeline: TBD
  • Cost: TBD
  • Funding source: Harris County Precinct 3
Gosling Road, West Rayford Road traffic signal
  • Project: The existing traffic signal at the intersection of Gosling Road and West Rayford Road will be replaced with a new mast-arm traffic signal.
  • Update: This project is out for construction bids.
  • Timeline: Estimated completion by the first quarter of 2025
  • Cost: TBD
  • Funding source: Harris County Precinct 3
Ongoing projects

Hufsmith-Kohrville Road, Segment 2
  • Project: Hufsmith-Kohrville Road will be widened from a two-lane asphalt roadway to a four-lane concrete boulevard with storm sewer and sidewalk from south of Rolling Glen Lane to north of Ezekiel Road.
  • Update: This project is under construction.
  • Timeline: Estimated completion by the first quarter of 2025
  • Cost: $12.5 million
  • Funding source: Harris County Precinct 3
Treaschwig Road, Segment 1A
  • Project: Treaschwig Road will be widened from a two-lane asphalt roadway to a four-lane concrete boulevard with storm sewer and sidewalk from west of Aldine Westfield Road to west of Cypress Creek.
  • Update: This project is under construction.
  • Timeline: Estimated completion by the second quarter of 2026
  • Cost: $19.9 million
  • Funding source: Harris County Precinct 3