Here's the latest information on four transportation projects in the Spring and Klein area. This list is not comprehensive.

Upcoming projects

1. Cypresswood Drive, Purple Wisteria Lane traffic signal installation

Project: A new mast arm traffic signal will be installed at the intersection of Cypresswood Drive and Purple Wisteria Lane.

Update: This project is in the design phase.2. Ella Boulevard, Falvel Road sidewalk construction


Project: This project will construct sidewalks on both sides of Ella Boulevard and Falvel Road from Spring Cypress Road to FM 2920, and reconstruct the existing sidewalk along the east side from Sapling Trail Court to Spring Cypress Road.

Update: This project is in the design phase.
  • Timeline: Estimated completion by the fourth quarter of 2024
  • Cost: TBD
  • Funding source: Harris County Precinct 3
3. Kuykendahl Road, Alvin A. Klein Drive traffic signal installation

Project: A new mast-arm traffic signal will be installed at the intersection of Kuykendahl Road and Alvin A. Klein Drive.

Update: This project is in the design phase.
  • Timeline: estimated completion by the fourth quarter of 2024
  • Cost: TBD
  • Funding source: Harris County Precinct 3
Ongoing projects


4. Treaschwig Road, Segment 1A

Project: Treaschwig Road will be widened from a two-lane asphalt roadway to a four-lane concrete boulevard with storm sewer and sidewalks from west of Aldine-Westfield Road to west of Cypress Creek.

Update: This project is under construction.
  • Timeline: estimated completion by the fourth quarter of 2025
  • Cost: $18.9 million
  • Funding source: Harris County Precinct 3