Ongoing projects
1. Hufsmith-Kohrville Road, Segment 2
Project: Hufsmith-Kohrville Road will be widened from a two-lane asphalt roadway to a four-lane concrete boulevard with storm sewer and sidewalk from south of Rolling Glen Lane to north of Ezekiel Road.
Update: This project is under construction.
- Timeline: estimated completion by the first quarter of 2025
- Cost: $12.5 million
- Funding source: Harris County Precinct 3
Project: Flashing lights and sidewalk will be installed along TC Jester Boulevard between Winding Ridge Drive and Bur Oak Drive.
Update: This project is under construction.
- Timeline: estimated completion by second quarter of 2024
- Cost: $120,000
- Funding source: Harris County Precinct 3
3. Cypresswood Drive, Cutten Road/Schroeder Road traffic signal
Project: This project will rebuild the traffic signal at the intersection of Cypresswood Drive and Cutten Road/Schroeder Road.
Update: This project is in the design phase.
- Timeline: estimated completion by the first quarter of 2025
- Cost: TBD
- Funding source: Harris County Precinct 3
Project: Substandard construction of the southbound departure lanes of the Stuebner Airline bridge over Cypress Creek will be repaired.
Update: This project is in the design phase.
- Timeline: estimated completion by the second quarter of 2025
- Cost: TBD
- Funding source: Harris County Precinct 3