Curious about what ongoing and upcoming transportation projects are happening in your area? Here's the latest information on four Spring-area transportation projects.

Upcoming projects

Birnam Wood Boulevard Segment 1 expansion


Harris County Precinct 3 officials are studying a project to expand Birnam Wood Boulevard to a four-lane concrete paved section between north of Hickorygate Drive and south of Otto Road. The project would also include traffic signal and drainage improvements and additions as needed. Construction is expected to take less than one year to complete.

Timeline: fourth quarter 2024- second quarter 2025


Cost: $3.5 million

Funding source: Harris County Precinct 3

Boudreaux Road widening

Harris County Precinct 3 is studying a project to expand Boudreaux Road to a four-lane concrete pavement section between Old Boudreaux Lane and Gleannloch Forest Drive at the Grand Parkway. The project would also include traffic signal and drainage improvements and additions as needed. Construction is expected to take just over one year to complete.


Timeline: second quarter 2025- third quarter 2026

Cost: $12.2 million

Funding source: Harris County Precinct 3

Spring Stuebner Road expansion


Harris County Precinct 3 is studying a project that would expand Spring Stuebner Road from a two-lane roadway to a four-lane concrete road from west of Leitner Lane to the Grand Parkway. Existing drainage and traffic signals will also be improved and added as needed. Precinct 3 officials said construction on this project is expected to take roughly one year to complete.

Timeline: second quarter 2025- second quarter 2026

Cost: $8.1 million

Funding source: Harris County Precinct 3


West Riley Fuzzel Road expansion

Harris County Precinct 3 is studying a project that would expand West Riley Fuzzel Road from a two-lane roadway to a four-lane concrete boulevard between I-45 and 200 feet west of West Hardy Road. Precinct 3 officials said the study phase is expected to wrap up by second quarter 2024; a construction timeline had not been announced as of press time.

Timeline: study phase to conclude by second quarter 2024; construction timeline TBD

Cost: $9.2 million


Funding source: Harris County Precinct 3