Curious about what ongoing and upcoming transportation projects are happening in your area? Below are four Spring and Klein based projects that include the scope, timeline, cost and funding source.

Ongoing projects

FM 2920 improvements


Construction is nearing completion on a project to enhance safety along FM 2920 between North Willow Street in Tomball and I-45 in Spring by adding continuous raised medians, improving traffic signals and adding right-turn lanes along the corridor. Bambi Hall, a public information officer with the Texas Department of Transportation, said work on the project was substantially completed in May, and final inspections are all that remain.

Timeline: February 2022-mid-2023


Cost: $3.6 million

Funding sources: 80% federal, 20% state

Upcoming projects

FM 1960 widening


As utility relocations continue, a project to expand FM 1960 between Centerfield Drive and Cutten Road is scheduled to go out for bids in August. The project will add a through lane east- and westbound on FM 1960 from the Willowbrook Mall center entrance to Cutten Road and add new pavement, continuous sidewalks, traffic signals and drainage improvements.

Timeline: advertising for bids in August, construction in 28 months

Cost: $20 million

Funding sources: 80% federal, 20% state


Grand Parkway widening

A two-part project to expand the Grand Parkway from four to six lanes and replace the grassy median with a concrete barrier is expected to begin next year. Segment A will run between Hwy. 249 and Kuykendahl Road and is scheduled to begin in 2024. Segment B will run from Kuykendahl Road to Holzwarth Road and is scheduled to begin in 2025.

Timeline: scheduled to begin in 2024 (Segment A) and 2025 (Segment B), construction in three years

Cost: $65.34 million (Segment A), $45.94 million (Segment B)


Funding source: TxDOT

Hufsmith-Kohrville Road widening

Two Harris County Precinct 3 projects to widen Hufsmith-Kohrville Road from south of Rolling Glen Lane to north of Ezekiel Road (Segment A) and from north of Ezekiel Road to north of Boudreaux Road (Segment B) are in the design phase, which is expected to wrap up by the fourth quarter of 2023. The projects would widen Hufsmith-Kohrville Road from a two-lane road to a four-lane road with storm sewers and sidewalks.

Timeline: TBD


Cost: $9.4 million (Segment A), $10.6 million (Segment B)

Funding source: Harris County Precinct 3