Gosling Road from West Rayford Road to Creekside Forest Drive will be upgraded to a four-lane concrete boulevard section for an estimated cost of $7.3 million, which will be funded by Harris County Precinct 3. Construction began in the second quarter of 2021 and will include improved drainage and added or altered traffic signals as needed. The bidding process began Feb. 5, 2021, while construction is expected to wrap up by the third quarter of this year.

Timeline: second quarter 2021-third quarter 2022

Cost: $7.3 million

Funding source: Harris County Precinct 3