Beltway 8 improvements

Work continues on a project to improve intersections and traffic signals along the Beltway 8 frontage road between West Gulf Bank Road and TC Jester Boulevard.

Timeline: Aug. 13, 2019-March 2022

Cost: $3 million

Funding sources: Harris County Precinct 4, Texas Department of Transportation




Hwy. 6, FM 1960 improvements

Construction is underway on a project to improve intersections and modify traffic signals along Hwy. 6 between West Little York and West roads and on FM 1960 between Fallbrook and Kenswick drives.

Timeline: Aug. 13, 2019-March 2022


Cost: $2 million

Funding sources: Precinct 4, TxDOT