A notice to proceed with construction was issued April 13 on a project to widen Riley Fuzzel Road from a two-lane asphalt roadway to a five-lane concrete paved section with improved drainage between Elm Street and the Hardy Toll Road. The project will also realign Riley Fuzzel Road and West Hardy Street to incorporate a four-way intersection, close the railroad crossing at Caroline Street and open a new railroad crossing north of Riley Fuzzel Road.

Timeline: April 13, 2020-March 2021

Cost: $5.02 million

Funding source: Harris County Precinct 4