Construction wrapped up in late June on a project to widen Gosling Road to a four-lane concrete section with improved drainage between Mossy Oaks and West Rayford roads. Originally slated for completion in late 2019, the project has been delayed by inclement weather, said Pamela Rocchi, the director of Harris County Precinct 4’s Capital Improvement Projects Division.
Timeline: March 21, 2018-June 29, 2020
Cost: $9.81 million
Funding source: Harris County Precinct 4