1. Harris County Precinct 1 is widening Walters Road between FM 1960 and Old Walters Road from two to four lanes as well as installing a new traffic signal and a left-turn lane at Bammel North Houston Road. The cost of the project is $11 million.
    Estimated timeline: April 2017-September 2018


2. Texas Department of Transportation’s $2.3 million Statewide Curb Ramp Project on FM 1960, implemented to meet Americans with Disabilities Act requirements, has resumed construction after having been delayed by utility conflicts, TxDOT Public Information officer Danny Perez said.
Estimated timeline: October 2016-early 2019

3. Allgood Construction began work on a $9.4 million Harris County Precinct 4 project in March to widen the Gosling Road bridge across Willow Creek and upgrade the two-lane asphalt road to four concrete lanes between West Mossy Oaks and West Rayford roads in Spring.
Estimated timeline: March 21-August 2019