The city of Pearland authorized a contract Nov. 7 with InfraTech Engineers & Innovators LLC for designing a Pearland Parkway and Broadway Street intersection construction project.

The project will consist of adding a second northbound left-turn lane on Pearland Parkway, a right-turn lane on north and southbound Pearland Parkway, and the relocation of sidewalk ramps and signal masts to accommodate the changes.



According to a document summarizing the project, the total budget for the project is about $2 million, and the total expenditures as of Nov. 7 are about $1.6 million: $1.3 million on construction, $200,000 on land and $127,651 on the design contract.

Funding primarily comes from the city's certificates of obligation, a flexible form of borrowed funds that do not require voter approval before use, unlike general obligation bonds.


The document states that the design schedule is a seven-month period and that the construction phase should begin November 2023 and last about six months.

This project comes after another Pearland Parkway expansion project adding a roundabout by McHard Road was completed Aug. 12. McHard is also undergoing an expansion expected to be complete by early 2023.