Thirst for resources: Population boom brings need for multimillion-dollar water infrastructure development

The development boom in Pearland and Friendswood has attracted more health care options, retailers and tax dollars to improve the quality of life for residents, but the additional rooftops mean increasing pressure on water and sewer infrastructure.

The development boom in Pearland and Friendswood has attracted more health care options, retailers and tax dollars to improve the quality of life for residents, but the additional rooftops mean increasing pressure on water and sewer infrastructure.

Quenching


The development boom in Pearland and Friendswood has attracted more health care options, retailers and tax dollars to improve the quality of life for residents, but the additional rooftops mean increasing pressure on water and sewer infrastructure.


The city of Pearland is trying to stay ahead of the population curve as developers snatch up undeveloped plots. But the city may be unable to quench the thirst of its growing population within five years without massive investments in its water and sewer infrastructure.


“At the end of the day, water is going to dictate growth in the area,” Pearland Public Works Director Eric Wilson said.


And in Friendswood, a city of less than 40,000 resident, the public works department is investing heavily in the city’s sewer system to increase its capacity while positioning the city for additional expansions in the future.


A thirsty population


Pearland is investing nearly $160 million in a new surface water treatment facility near Airline Road South and Southfork Drive in Pearland. The new facility, which is in the design phase, will not only meet future water demands but could even become a regional plant, supplying cities like neighboring Manvel and Alvin that, too, are quickly growing, according to the city.


The city’s population skyrocketed from roughly 38,000 in 2000, according to the U.S. Census Bureau, to about 120,000 as of January, according to the city’s estimates.


“[The water plant] is critical, not just to Pearland but also for the region,” Wilson said. “Short-term planning in the world of water and wastewater is 20 years. I try to look at stuff 50 to 100 years. That’s really getting the crystal ball out and trying to dial it out.”


The city’s maximum capacity to date is 34 million gallons per day, more than half of which is supplied by groundwater. Currently, the only sources of surface water are the city of Houston and the Clear Brook City Municipal Utility District.


The new surface water treatment plant is expected to provide up to 20 million gallons of additional drinking water per day from the Brazos River through a contract with the Brazos River Water Authority. The city is investing in the first phase of development, which is slated for completion in 2022 and will provide 10 million gallons per day. Depending on growth needs at the time, officials can decide to postpone phase two, which would add an additional 10 million gallons per day.


Rumblings of a surface water treatment facility began more than a decade ago. Seeing the growth on the horizon, officials purchased the rights to an additional 20 million gallons per day from the Brazos River Water Authority in 2006 and purchased land for the water plant in 2008.


“It’s one of the largest undertakings the city has taken to date,” Pearland Assistant City Manager Trent Epperson said. “There’s a lot of forethought that city leaders took … and those things put us in a really good position to meet our needs for the next several years.”


The plant and a modern water metering system will be funded by a $160 million loan from the Texas Water Development Board. The city received approval in November for a multi-year commitment from the state’s Drinking Water State Revolving Fund. Municipalities that are approved are able to finance loans at below market interest rates.


“I think Pearland is a perfect example of a community that is identifying what its issues are,” said Jessica Zuba, deputy executive administrator of water supply and infrastructure at the Texas Water Development Board. “They went to the extent of doing a comprehensive plan to assess what their needs are going to be.”


In nearby Friendswood, officials have invested $3.6 million to expand the capacities of its two water plants by 227,000 gallons. The city upgraded both plants with concrete buildings to protect them—along with the pumps, chemicals and electronics—from future hurricanes as well as upgraded fencing to meet regulatory requirements.


The city also upgraded the backup generators and added four total pumps at the facilities.


“We’ve had a lot of growth,” said Patrick Donart, Friendswood city engineer and public works director. “What we’ve been doing is mainly looking at the infrastructure we have and try to make it better and prioritizing the needs.”


The funds come from city water and sewer bonds with additional funding from local municipal utility districts.


Wastewater needs


Drinking water is not the only thing concerning officials as they plan for future growth. Increasing water output to residents means more water will find its way down drains and into wastewater, or sewage, treatment facilities.


In Pearland, the public works and engineering departments broke ground in August on a $44.7 million expansion of the Reflection Bay Water Reclamation Facility. The expansion, which is projected to be complete in 2019, is expected to increase capacity from 2 million gallons to 6 million gallons a day, according to the city.


The updated Reflection Bay facility will have additional odor control units, additional grit removal, and improved disinfection and filtration systems that improve the quality of the water that the city discharges into Clear Creek.


The project is funded by a separate loan of $61.2 million from the Texas Water Development Board.


The city of Friendswood is investing more than $6 million in improving its wastewater systems.


The public works department is working on improvements to three of the city’s 39 lift stations, which serves as collection points before pumping sewage from a lower to higher elevation to send to a treatment facility.


One lift station was completed in late 2016, a second was completed in early February and the third will break ground later this year. After all three are completed, the city will have total capacity for 27 million gallons per day, up from 18 million gallons per day.


“The city is always looking at trying to upgrade their sanitary sewer and water systems,” Donart said. “Some things are mandated by the state; some are mandated by development.”


Regulatory requirements included increased security fencing and improved generators in case of an emergency.


Future projects


Both water and wastewater infrastructure projects are driven by population demand.


People are expected to keep moving into Pearland until growth fizzles at an estimated 220,000 residents between 2040 and 2050, according to the city. Most of the growth has moved to the east side of Pearland as Shadow Creek Ranch approaches build-out, so the city has started working on projects years down the road.


Pearland is designing potential improvements to either Barry Rose Wastewater Treatment Plant or the John Hargrove Environmental Complex for a future expansion project, depending on the growth trajectory in east Pearland, according to the city. Down the line, Pearland may decommission two of its smaller wastewater facilities to grow and regionalize its other facilities.


“[The population boom] has moved from the west side over to [the east] side. That has triggered us because we don’t want to get caught behind the curve,” Wilson said.


In addition to multimillion-dollar facility improvements, Pearland is investing in older neighborhoods near Old Townsite, which was built in the ’60s, to repair or replace old water and sewer lines.


“Trying to split our efforts between growth and recapitalization is a balancing act. It’s something we strive to do,” Wilson said.



MOST RECENT

As of June 4, 14 COVID-19 deaths have been confirmed and 56 residents and staff are being monitored at the center. (Community Impact staff)
Harris County coronavirus count: Outbreak reported at Humble rehab facility

As of June 4, 14 COVID-19 deaths have been confirmed and 56 residents and staff are being monitored at the center.

Vitality Bowls in Friendswood donated over 150 smoothies to health care workers. (Courtesy Vitality Bowls)
Friendswood business gives back to health care workers

The business plans on donating food to nursing homes next.

CMS also unveiled an interactive map that lets users search any nursing home in the U.S. to see its COVID-19 cases. (Courtesy Adobe Stock)
CMS reports 321 coronavirus deaths in Texas nursing homes, nearly 32,000 nationwide

CMS also unveiled an interactive map that lets users search any nursing home in the U.S. to its COVID-19 cases.

While the Texas Supreme Court's 15th Emergency Order issued May 14 allowed residential eviction proceedings to resume statewide beginning May 19 following a two-month hiatus, the order does not require those proceedings to resume. (Community Impact Newspaper staff)
Hidalgo, Turner request eviction moratorium be extended through Aug. 24

In hopes of avoiding a new wave of homelessness plaguing Harris County, Houston Mayor Sylvester Turner and Harris County Judge Lina Hidalgo have requested all justices of the peace countywide to postpone eviction hearings until late August.

Total cases have risen to 13,268 in Harris County, 7,812 of which are considered active while 5,215 are confirmed to have recovered. A total of 241 people are confirmed to have died from the coronavirus in the county.(Community Impact staff)
Harris County coronavirus count: 241 new cases, 5 deaths confirmed June 3

Meanwhile, Texas Gov. Greg Abbott said 45% of new cases statewide between May 26 and June 2 can be tied to prisons, jails, meat packing plants or nursing homes.

Texas Gov. Greg Abbott announced Phase 3 of his Open Texas plan June 3. (Brian Rash/Community Impact Newspaper)
Gov. Greg Abbott's June 3 guidelines allow most Texas businesses to operate at 50% capacity

Texas Gov. Greg Abbott continues to lift coronavirus-related business restrictions.

Here are the coronavirus updates to know today in Brazoria County. (Community Impact staff)
Brazoria County coronavirus count: 16 new cases reported June 3

11 of the new cases are Pearland residents.

Participants held fists in the air during a moment of silence at a June 2 protest over the death of George Floyd. (Emma Whalen/Community Impact Newspaper)
Q&A: Criminal justice research expert weighs in on George Floyd protests and the sentiments driving them

"I think the data is clear and convincing that there is a problem. I think that we now have societal consensus of that problem and accepting that data."

(Adriana Rezal/Community Impact Newspaper)
PHOTOS: Scenes from the downtown Houston march for George Floyd

People of all ages, colors and creeds packed downtown Houston June 2 to march in memory of former Houston resident George Floyd.

(Community Impact Newspaper staff)
Brazoria County coronavirus count: 12 new cases June 2

Eleven of the 12 reported cases are confirmed.

As protests over the death of George Floyd continue, the Harris County Public Health Department released a statement asking people to take precautionary measures if they plan to attend a protest. (Community Impact Newspaper staff)
Harris County coronavirus count: County tops 350 new cases for second straight day

As protests over the death of George Floyd continue, the Harris County Public Health Department released a statement asking people to take precautionary measures if they plan to attend a protest.

Nola Z. Valente/Community Impact Newspaper
60,000 gather in downtown Houston June 2 in solidarity with George Floyd's family

Among a series of marches across the U.S. to honor George Floyd, his hometown of Houston turned out in the thousands June 2.