Curious as to what new businesses and renovations are underway or coming to Pearland and Friendswood? The following projects have been filed in the last month through the Texas Department of Licensing and Regulation. The following information may be subject to change.

1. Kroger: 8323 Broadway St., Pearland

Type of work: renovation/alteration

Timeline: Sept. 26-Oct. 28


Estimated cost: $250,000

2. Torchy’s Tacos: 2800 E. Broadway St., Ste. P, Pearland

Type of work: renovation/alteration

Timeline: Sept. 19, 2022-Jan. 9, 2023


Estimated cost: $750,000

3. Keystone: 1424 N. Main St., Pearland

Type of work: new construction

Timeline: Oct. 1, 2022-June 30, 2023


Estimated cost: $8.4 million

4. Kimley Horn: 11233 Shadow Creek Parkway, Pearland

Type of work: renovation/alteration

Timeline: Sept. 22, 2022-Jan. 23, 2023


Estimated cost: $330,000

5. Pearland Beauty: 2000 Reflection Bay Drive, Ste. 148, Pearland

Type of work: new construction

Timeline: Sept. 5-Nov. 28


Estimated cost: $150,000

6. Buc-ee’s: 11200 Broadway St., Ste. 2338, Pearland

Type of work: renovation/alteration

Timeline: Sept. 1-Dec. 1

Estimated cost: $375,000

7. Lonza Biologics: 14905 Kirby Drive, Pearland

Type of work: renovation/alteration

Timeline: Aug. 11, 2022-Jan. 30, 2023

Estimated cost: $1.6 million

8. Empire Custom Jewelry: 500 Baybrook Mall, Ste. 1092, Friendswood

Type of work: renovation/alteration

Timeline: Aug. 1-Oct. 1

Estimated cost: $150,000

9. Mid Haven Coffee: 106 Whispering Pines Ave., Friendswood

Type of work: new construction

Timeline: Aug. 23-Dec. 20

Estimated cost: $2 million

10. Dillard’s: 600 Baybrook Mall, Friendswood

Type of work: renovation/alteration

Timeline: Sept. 19-Oct. 28

Estimated cost: $51,295