Conroe | Montgomery Transportation Updates for February 2017 1. FM 1097 widening The Texas Department of Transportation broke ground in July on an FM 1097 expansion project between I-45 and Hwy. 75. The project will expand the roadway from two to four lanes and add a continuous left-turn lane. The project includes new sidewalks. Construction is about 25 percent complete. Timeline: July 11, 2016-first quarter 2018 Cost: $3.5 million Funding sources: TxDOT 2. FM 149 improvements TxDOT is working on a 13-month resurface and repair project on 10 miles of FM 149 between FM 1791 and FM 1097. The project will also add a 5-foot-wide shoulder throughout that length of roadway and is intended to improve traffic safety throughout the area. The project is about 50 percent complete but is on hiatus while nearby utilities are relocated. Timeline: 2016-second quarter 2017 Cost: $10.2 million Funding sources: federal grants, TxDOT 3. FM 3083 railroad overpass  TxDOT has undertaken a project that will widen FM 3083 from two to four lanes and build a bridge over the Union Pacific Corp. railroad tracks east of Hwy. 75. The agency has already widened FM 3083 in a separate project from I-45 to the starting location of the overpass bridge. The project has reached 30 percent completion and is expected to take about two years to finish. Timeline: May 2016-third quarter 2018 Cost: $13.1 million Funding sources: TxDOT 4. Hwy. 105 improvement project  The city of Conroe started construction on a Hwy. 105 improvement project Oct. 10. The project adds a raised median throughout the roadway from I-45 to Frazier Street. The median will limit left-hand turns to designated intersections for transit safety purposes. Construction includes sidewalks on each side of the roadway. Timeline: Oct. 10, 2016-summer 2017 Cost: $3.5 million Funding sources: city of Conroe, TxDOT 5. West Side Loop completed A new roadway that connects FM 1097 to Old Montgomery Road near I-45 in Willis was opened to traffic on Jan. 16. Crews also added a new stop sign at the intersection with FM 1097. The roadway also makes it possible for TxDOT to convert the I-45 southbound feeder road at the FM 1097 intersection into a one-way road. TxDOT plans for the feeder road project are in the design phase. Timeline: Summer 2016-Jan. 16, 2017 Cost: $1.2 million Funding sources: Montgomery County, city of Willis Conroe | Montgomery Transportation Updates for February 2017