Harris County


Harris County Precinct 4 has proposed a widening and extension of Cypress N. Houston/Lou Edd Road as a four-lane concrete pavement section from Jones Road to FM 1960 in Houston.

Cypress N. Houston/LouEdd Road improvements


Harris County Precinct 4 has proposed a widening and extension of Cypress N. Houston/Lou Edd Road as a four-lane concrete pavement section from Jones Road to FM 1960 in Houston. The project is in the study phase, and a cost estimate for the project is expected to be released after the study phase is concluded.


Timeline: TBA






Cypress Rosehill Road wideningCypress Rosehill Road widening


Construction started in July on a Harris County Precinct 3 project to widen Cypress Rosehill Road from two to four lanes. The work being done from Lake Cypress Hill Road in Cypress to the Grand Parkway will be ongoing for the next year, according to officials. County officials estimate the project will cost around
$9.9 million.


Timeline: July 2016-third quarter 2017






Fairfield Place wideningFairfield Place widening


Harris County Precinct 3 is widening Fairfield Place to a four-lane boulevard from Cumberland Ridge Drive to Schiel Road in Cypress. Construction started Nov. 7 and is on target to be completed the first week of February. Officials estimate the project to cost around $1.07 million.


Timeline: November-February






Grant Road wideningGrant Road widening


Harris County precincts 3 and 4 are working on two projects that will widen Grant Road between Spring Cypress Road and Lakewood Forest Drive in Cypress. Precinct 3 will widen the road from two to four lanes between Lakewood Forest Drive and Old Kluge Road. Precinct 4 will widen it from Old Kluge to Spring Cypress roads. Precinct 4 awarded a 720-day contract on Oct. 11. Construction on the Precinct 3 section will begin in early 2017.


Timeline: October 2016-late 2018






Greenhouse Road extensionGreenhouse Road extension


Harris County Precinct 3 is partnering with developer Caldwell Companies on a project to extend Greenhouse Road north to Mound Road in Cypress as a two-lane concrete half-boulevard. Caldwell has already completed its portion of the project, and Harris County intends to complete a two-lane bridge to connect the road over Cypress Creek. Caldwell officials estimated the company's part of the project to cost around $10 million.


Timeline: April 2016-spring 2017






Huffmeister Road extensionHuffmeister Road extension


Harris County Precinct 4 has completed the study phase and entered the design phase of a Huffmeister Road project that would extend the roadway from where it ends at Hwy. 6 to West Road in Houston as a four-lane concrete pavement section. Officials hope to send the project out for bid in 2018. County officials estimate the project could cost around $2.5 million.


Timeline: TBA






Louetta Road extensionLouetta Road extension


Harris County Precinct 4 is working to extend Louetta Road as a four-lane concrete boulevard from Blanco Trails Lane to Telge Road in Cypress. Construction on the project was initiated by Unitas Construction on Aug. 9. The project also includes a new traffic signal at Louetta and Telge roads. It is estimated to cost $2.3 million.


Timeline: August-January






Telge Road wideningTelge Road widening


A five-segment Telge Road widening project by Harris County Precinct 4 would expand the road from two to four concrete lanes between south of Little Cypress Creek in Cypress and FM 2920 in Tomball. Construction could start as early as the end of 2017. A cost estimate for the project is expected to be released following the study phase.


Timeline: TBA