Several road reconstruction, widening and repaving projects are on the horizon for the city of Humble. Here's the latest information on a few city projects.

South Houston Avenue widening, reconstruction

Project: This project will widen South Houston Avenue between Will Clayton Parkway and Atascocita Road from the existing two-lane asphalt roadway to a three-lane concrete roadway with curb and gutter. The project will also include a new traffic signal system and drainage improvements, including the installation of underground storm sewers, inlets and ditch regrading.

Update: Surveying is complete and engineering for the project was 10% complete as of the January 2025 monthly report from the city of Humble’s Public Works Department.
  • Timeline: January 2026-January 2028
  • Cost: $1,132,360
  • Funding source: City of Humble
Meek and Manning roads paving, drainage improvements

Project: This project will repave existing asphalt streets including Meek Road and Manning Road between North Houston Avenue and Townsen Boulevard. The project will also include the installation of roadside drainage culverts, new water lines and fire hydrants along Meek Road.


Update: Surveying is complete and engineering for the project was 10% complete as of the January 2025 report.
  • Timeline: August 2025-January 2026
  • Cost: $241,750
  • Funding source: City of Humble
McDugald Road, Sharon Drive and Carolyn Court reconstruction

Project: This project will replace existing asphalt streets with concrete curb and gutter including McDugald Road, Sharon Drive and Carolyn Court. The project will also replace water lines and fire hydrants along McDugald Road.

Update: Surveying is complete and engineering for the project was 30% complete as of the January 2025 report.
  • Timeline: August 2025-May 2026
  • Cost: $369,500
  • Funding source: City of Humble