Here's the latest information on four transportation projects in the Lake Houston area. This list is not comprehensive.

Upcoming projects

West Lake Houston Parkway Sidewalk, Phase 1B
  • Project: Sidewalks will be constructed on both sides of West Lake Houston Parkway from Will Clayton Parkway to Aerobic Drive.
  • Update: This project is in the design phase.
  • Timeline: TBD
  • Cost: TBD
  • Funding source: Harris County Precinct 3
Will Clayton Parkway Sidewalk
  • Project: Sidewalks will be constructed on Will Clayton Parkway from Tabor Brook Drive to Garbit Drive.
  • Update: This project is in the design phase.
  • Timeline: TBD
  • Cost: TBD
  • Funding source: Harris County Precinct 3
Ongoing projects

West Lake Houston Parkway Sidewalk, Phase 1A
  • Project: Sidewalks will be constructed on both sides of West Lake Houston Parkway from Madera Run Parkway to Will Clayton Parkway.
  • Update: This project is under construction
  • Timeline: Estimated completion in the fourth quarter of 2024
  • Cost: $1.1 million
  • Funding source: Harris County Precinct 3
Madera Run Parkway expansion
  • Project: Madera Run Parkway will be widened from two lanes to a four-lane concrete boulevard separated by a green median between Radura Road and Hickory Arroyo Drive.
  • Update: This project is under construction.
  • Timeline: Estimated completion in the fourth quarter of 2024
  • Cost: $1.2 million
  • Funding sources: Harris County Precinct 3, Harris County Municipal Utility District No. 504