Upcoming projects
West Lake Houston Parkway Sidewalk, Phase 1B
- Project: Sidewalks will be constructed on both sides of West Lake Houston Parkway from Will Clayton Parkway to Aerobic Drive.
- Update: This project is in the design phase.
- Timeline: TBD
- Cost: TBD
- Funding source: Harris County Precinct 3
- Project: Sidewalks will be constructed on Will Clayton Parkway from Tabor Brook Drive to Garbit Drive.
- Update: This project is in the design phase.
- Timeline: TBD
- Cost: TBD
- Funding source: Harris County Precinct 3
West Lake Houston Parkway Sidewalk, Phase 1A
- Project: Sidewalks will be constructed on both sides of West Lake Houston Parkway from Madera Run Parkway to Will Clayton Parkway.
- Update: This project is under construction
- Timeline: Estimated completion in the fourth quarter of 2024
- Cost: $1.1 million
- Funding source: Harris County Precinct 3
- Project: Madera Run Parkway will be widened from two lanes to a four-lane concrete boulevard separated by a green median between Radura Road and Hickory Arroyo Drive.
- Update: This project is under construction.
- Timeline: Estimated completion in the fourth quarter of 2024
- Cost: $1.2 million
- Funding sources: Harris County Precinct 3, Harris County Municipal Utility District No. 504