Upcoming projects
West Lake Houston Parkway sidewalk
- Project: Sidewalks will be constructed along West Lake Houston Parkway from Summer Lake Ranch Drive to Lakewood Pines Boulevard.
- Update: This project is in the design phase.
- Timeline: third quarter 2024-fourth quarter 2024
- Cost: TBD
- Funding source: Harris County Precinct 3
- Project: The traffic signal will be rebuilt at the intersection of West Lake Houston Parkway and Firesign Drive.
- Update: This project is in the design phase.
- Timeline: first quarter 2025-second quarter 2025
- Cost: TBD
- Funding source: Harris County Precinct 3
- Project: The traffic signal will be rebuilt at the intersection of West Lake Houston Parkway and Kings River Drive/Kings Lake Estates Boulevard.
- Update: This project is in the design phase.
- Timeline: first quarter 2025-second quarter 2025
- Cost: TBD
- Funding source: Harris County Precinct 3
Townsen Park-N-Ride Multimodal Connector
- Project: An 8-foot-wide concrete hike and bike trail will be constructed to connect the Townsen Park-and-Ride to the I-69 Historical Pedestrian Bridge Metro Park-and-Ride.
- Update: This project is under construction.
- Timeline: March 2024-third quarter 2025
- Cost: $1.5 million
- Funding sources: Harris County Precinct 3, Texas Department of Transportation