Here's the latest on six Lake Houston-area transportation projects.

Ongoing projects

Northpark Drive overpass


Project: This project will expand Northpark Drive from four to six lanes between Hwy. 59 and Russell Palmer Road, and add an overpass over the Union Pacific Railroad and Loop 494.

Update: According to a November newsletter from Houston Mayor Pro Tem Dave Martin, Harper Bros.—the project contractor—has finished clearing the areas for the two detention ponds at the front of Northpark Drive and will soon begin excavation work. The contractor has also begun work on sidewalks, and planning for Phase II of the project—east of the Kingwood diversion ditch—has begun.Atascocita Road, Blackstone Trails Drive intersection improvements


Project: This project will install a new traffic signal at the intersection of Atascocita Road and Blackstone Trails Drive.

Update: In a Nov. 6 email, Precinct 3 Communications Manger Jeannie Peng said this project is on track to be completed by the end of November.FM 1960 widening

Project:
This two-part project will widen FM 1960 from a four-lane asphalt roadway to a six-lane divided concrete roadway with raised median, curb and gutter, channelized left-turn lanes and a 5-foot sidewalk on both sides of the roadway. Segment A runs from Business FM 1960 to east of Twigsworth Lane, while Segment B continues to the western approach of the McKay Bridge at Lake Houston. Segment B will also include the construction of a new bridge that will span over Atascocita Road, West Lake Houston Parkway and Farmingham Road.

Update: In a Nov. 8 email, Bambi Hall, a public information officer with the Texas Department of Transportation, said construction is underway and expected to continue on the project through 2025.
  • Timeline: late 2021-December 2025 (Segment A), late 2021-spring 2024 (Segment B)
  • Cost: $58.2 million (Segment A), $70 million (Segment B)
  • Funding source: TxDOT
Recently completed


Will Clayton Parkway sidewalk installation


Project: This project will install a 500-foot section of sidewalk on the south side of Will Clayton Parkway from Cricket Mill Drive to Woodland Hills Drive.

Update: In a Nov. 6 email, Peng said this project had been completed.
  • Timeline: July-August
  • Cost: $50,000
  • Funding source: Harris County Precinct 3
Atascocita Road restriping

Project: This project will restripe Atascocita Road from Old Humble Road to just south of FM 1960.


Update: In a Nov. 6 email, Peng said this project had been completed.
  • Timeline: July-August
  • Cost: $200,000
  • Funding source: Harris County Precinct 3
Loop 494 expansion

Project: This project will expand Loop 494 between a half-mile north of Kingwood Drive and north of Sorters McClellan Road.

Update: In a Nov. 8 email, Hall said construction on this project wrapped up in September and the contractor is finishing the final punchlist.
  • Timeline: July 15, 2019-Sept. 1, 2023
  • Cost: $17.56 million
  • Funding source: 80% federal, 20% state