A project to expand Sorters McClellan Road to four lanes with a center turn lane between FM 1314 and Northpark Drive is on hold due to utility conflicts. According to Hugo Sanchez, the projects and logistics coordinator for Montgomery County Precinct 4, construction will begin on (A) Segment 1—FM 1314 to south of Lowe Road—once utility relocations are completed in October, while (B) Segment 2—south of Lowe Road to Northpark Drive—will go out for bid once utility conflicts are resolved.

Timeline: January 2023-August 2023

Cost: $6.8 million (Segment 1), $7.4 million (Segment 2)

Funding source: Montgomery County Precinct 4 road bonds