Montgomery County Precinct 4 began construction on (A) Segment 1 of the Sorters McClellan Road project Jan. 24 and began receiving bids for (B) Segment 2 in March. The project will expand the road to four lanes with a center turn lane between FM 1314 and Northpark Drive. Segment 1 runs from FM 1314 to south of Lowe Road, and Segment 2 continues to Northpark Drive.
Timeline: Jan. 24, 2022-January 2023 (Segment 1), TBA (Segment 2)
Cost: $6.8 million (Segment 1), $7.4 million (Segment 2)
Funding source: Montgomery County Precinct 4