Construction on Harris County Precinct 2’s Madera Run Parkway expansion began last May and will finish this year. It expands the road from two to four lanes between Kings Parkway and Boundary Waters Lane, adds a median and creates a bridge near Fernbank Forest Drive.

Timeline: May 26, 2020-May or June 2021

Cost: $3.75 million

Funding source: Harris County Precinct 2

Correction: The original version of this story incorrectly stated the project would be completed in the third quarter of 2021. At the time, the project was estimated to be completed in May or June.