TxDOT Public Information Officer Emily Black said utility issues delayed the completion date from the second quarter of 2021. The cost also increased slightly from $14.3 million to $15.1 million because TxDOT had to redesign a portion of the project to work around utility issues and reduce the effects on traffic, Black said.
Timeline: July 2019-third quarter 2021
Cost: $15.1 million
Funding source: TxDOT