Grand Parkway widening
The Texas Department of Transportation will add two more lanes to the Grand Parkway from FM 1093 to I-10. The cost has increased $18 million, and the timeline has been delayed six months since January, TxDOT Public Information Officer Deidrea George said via email. She cited inflation and redesign as reasons for the changes.
Cost: $103 million
Timeline: April 2023-April 2025
Funding sources: state, federal funds
First Street reconstruction
The project funded by the Katy Development Authority will begin at the end of November or mid-December, according to ARKK Engineers. It includes widening First Street from Bartlett Road to Avenue D by creating a center turn lane and adding a bridge over Cane Island Creek.
Cost: $2.71 million
Timeline: winter 2022-August 2023
Funding source: KDA cash funds