Crew have completed all the paving to widen Peek road into a four-lane boulevard between Clay Road and Grand Ventana Drive, Harris County engineer Jennifer Almonte said. As of March 25, crews are working on final drainage and detention work and a sidewalk at Grand Ventana Drive. Remaining projects include a final traffic switch to the new lanes, removing of temporary asphalt, completing medians and installing signs and striping.
Timeline: April 2019-second quarter 2020
Cost: $4.4 million
Funding source: Harris County