1. Johnny Ritas: 27120 Fulshear Bend Drive, Ste. 100, Fulshear
Type of work: renovation/alteration
Timeline: May 5-July 31
Estimated cost: $250,000
2. Contempo Builder Office: 21302 Provincial Blvd., Katy
Type of work: new construction
Timeline: May 2, 2022-Jan. 13, 2023
Estimated cost: $540,000
3. Broadstone Jordan Ranch Clubhouse: 29655 Jordan Crossing Blvd., Fulshear
Type of work: new construction
Timeline: April 1, 2022-April 1, 2024
Estimated cost: $1 million
4. Ivy Kids Early Learning Center Elyson: 23101 Beckendorf Road, Katy
Type of work: new construction
Timeline: Sept. 1, 2022-Sept. 30, 2024
Estimated cost: $2.5 million
5. Dogtopia: 6434 FM 1463, Fulshear
Type of work: new construction
Timeline: May 1-Nov. 30
Estimated cost: $500,000