1. Project Halo Brewing: 6520 Rogers Road, Ste. 500, Fulshear
Type of work: new construction
Timeline: Feb. 4-May 4
Estimated cost: $220,000
2. Action Behavior Center: 5433 N. Fry Road, Katy
Type of work: renovation/alteration
Timeline: Jan. 12-Sept. 12
Estimated cost: $350,000
3. The Shops at Market Place: 25116 Market Place Drive, Katy
Type of work: new construction
Timeline: March 1-June 1
Estimated cost: $1.3 million
4. Plaza at Elyson: 22225 FM 529, Katy
Type of work: new construction
Timeline: March 1-Aug. 1
Estimated cost: $1.2 million
5. Katy Gaston Urgent Care: 6940 Katy Gaston Road, Katy
Type of work: renovation/alteration
Timeline: Nov. 15-Jan. 17
Estimated cost: $310,700