1. No Yogurt: 94 W Grand Parkway S., Ste. 260, Katy
Type of work: new construction
Timeline: Feb. 1-June 1
Estimated cost: $120,000
2. Huggins Elementary School: 1 Huggins Drive, Fulshear
Type of work: additions to existing building
Timeline: Dec. 20-March 30
Estimated cost: $4.2 million
3. Preferred Urgent Care: 1259 FM 1463, Ste. 300, Katy
Type of work: renovation/alteration
Timeline: Jan. 31-April 30
Estimated cost: $209,000
4. Dynamic Tae Kwon Do: 25031 Westheimer Parkway, Ste. 800, Katy
Type of work: new construction
Timeline: Dec. 20-March 30
Estimated cost: $190,000
5. McFee Elementary School: 19315 Plantation Cove Lane, Katy
Type of work: renovation/alteration
Timeline: March 1-Aug. 1
Estimated cost: $7.2 million