1. BBC United: 4228 Clay Business Drive, Katy
Type of work: renovation/alteration
Timeline: Oct. 11-Dec. 13
Estimated cost: $176,000
2. Kingsland Medical Center: 23531 Kingsland Blvd., Ste. 200, Katy
Type of work: additions to existing building
Timeline: Nov. 10-May 10
Estimated cost: $230,000
3. The Goddard School: Lake Hill Farm Way, Fulshear
Type of work: new construction
Timeline: Oct. 1-30
Estimated cost: $2 million
4. Fulshear City Hall complex: 6450 Cross Creek Bend Lane, Fulshear
Type of work: renovation/alteration
Timeline: Nov. 1-May 13
Estimated cost: $7.2 million
5. Kizuki Ramen and Izakaya: 23220 Grant Circle Blvd., Ste. 140, Katy
Type of work: renovation/alteration
Timeline: Oct. 1-Feb. 1
Estimated cost: $500,000