1. Community Psychiatry—24275 Katy Fwy., Ste. 410, Katy
Type of work: Renovation/Alteration
Timeline: Start date is Nov. 11 and completion date is Feb. 1, 2022.
Estimated cost: $170,000
2. Bank of America Cross Creek Ranch—4826 FM 1463, Katy
Type of work: New construction
Timeline: Start date is Dec. 15 and completion date is Aug. 1, 2022.
Estimated cost: $2 million
3. La Michoacana Meat Market—3451, 3455 W. Grand Parkway N. Katy,
Type of work: New construction
Timeline: Start date is Dec. 1 and completion date is Aug. 15, 2022.
Estimated cost: $800,000
4. Reliant ABA Therapy—24210 Cinco Terrace Drive, Katy
Type of work: Renovation/Alteration
Timeline: Start date is Oct. 30 and completion date is Dec. 15.
Estimated cost: $150,000
5. Escalate Upward Executive Suites—4285 Katy Fwy., Ste. 400, Katy
Type of work: Renovation/Alteration
Timeline: Start date is Nov. 11 and completion date is is Jan. 1, 2022
Estimated cost: $1.2 million