Work on FM 1093, tollway project to continue into 2018

Workers prepare a segment of the new FM 1093 westbound frontage roads for the laying of the concrete to form the road. Before workers can pour concrete, a network of rebar is installed.

Workers prepare a segment of the new FM 1093 westbound frontage roads for the laying of the concrete to form the road. Before workers can pour concrete, a network of rebar is installed.

Work on Phase 1 of the FM 1093 frontage road and Westpark Tollway extension project began in February and is expected to continue through the end of 2017. As construction progresses, many safety issues have arisen causing county officials to encourage drivers along the corridor to find another route and also follow numerous safety tips.


“If there is another route to your home or your job, try to avoid [the construction area],” said Stacy Slawinski, an engineer with Fort Bend County. “In a perfect world, we could work 24 hours a day and get it done as soon as possible. Drivers need to be careful; there are a lot of workers out there.”


The project is expected to relieve congestion and enhance safety for the growing population that lives along FM 1093, which has seen thousands of homes constructed and numerous commercial developments sprout in the past 10 years, said Andy Meyers, Fort Bend County Precinct 3 commissioner.


Meyers said he and other public officials saw a need for widening FM 1093 and extending the Westpark Tollway more than a decade ago.


“Ten years ago, I recognized FM 1093 was going to be a very congested road; it was only two lanes,” Meyers said. “The county was approving housing developments in the area, and with a lot of houses and a lot of cars, we knew traffic would be an issue.”


The two-phase project has a total cost of $160 million and is funded jointly by the Texas Department of Transportation, Fort Bend County and the Fort Bend Toll Road Authority.



Work on FM 1093, tollway project to continue into 2018 Roots of the project


Meyers said the project to widen the more than 100-year-old FM 1093 and extend the toll road began to gain steam well before the Westpark Tollway opened in 2007.


“Once it was obvious that we were going to build an alternate route into Houston other than I-10, developers came out and began to buy land,” he said. “It was obvious to us how many homes would be built over 10 to 15 years. It’s probably the fastest-growing area in the whole state.”


Meyers said the project has been delayed due to a variety of issues, including initial problems with officials from the Federal Highway Administration.


Because a federal project requires an environmental impact study—usually a six-year process—Meyers said officials turned to TxDOT because FM 1093 is a state road. State roads require a less-time consuming environmental assessment, which allowed construction to begin more quickly, Meyers said.


Fort Bend County entered into a toll equity agreement with TxDOT to fund the project. Of the $160 million cost, TxDOT is providing $40 million, and the county is paying $120 million, Meyers said.


Phase 2 of the project, which has not been officially finalized, involves extending the two two-lane frontage roads from Cross Creek Ranch west to James Lane, Meyers said. There are no current plans to extend the Westpark Tollway past Cross Creek Ranch, he said.


“I don’t know what Fulshear’s desires are,” he said. “Some of the city fathers have expressed concern about having a toll road through the city.”


Meyers said the project is four years behind schedule due to various delays.


“I’m just trying to build a road, to widen a road,” he said. “It’s a simple process that has taken eight years. It is very frustrating.”



Work on FM 1093, tollway project to continue into 2018



The project


Richard Stolleis, an engineer with Fort Bend County who is heading the project, said Phase 1 will create four lanes of frontage road—two lanes each for eastbound and westbound traffic—from the existing end point of the Westpark Tollway to the entrance of Cross Creek Ranch.


Phase 1 also includes extending the Westpark Tollway 2.3 miles westward from its existing endpoint to the intersection of Spring Green Boulevard. The tollway will be four lanes—two lanes in both westbound and eastbound directions—with overpasses and Texas U-turns constructed at the intersection of Katy-Gaston Road and Spring Green Boulevard.


“The entire Phase 1 [segment] is about 4 miles long, but about 2.4 miles of it is toll lanes and frontage road,” Stolleis said. “The remainder of the project—1.6 miles—is frontage road only.”


Stolleis said the Phase 1 frontage roads are set to be completed by the end of August. The project has led to traffic delays from Spring Green Boulevard to the Grand Parkway as workers have narrowed lanes and installed concrete barriers.


“We should have traffic [able to travel] on the eastbound [frontage road] lanes by October,” he said.



Safety a concern


Maj. Chad Norvell of the Fort Bend County sheriff’s office said law enforcement officials have been concerned about safety issues in the construction zone since work began earlier this year.


“It is always congested and very busy. The hot spot we tend to get a lot of accidents is at Katy-Gaston Road [intersection with FM 1093], eastbound in the morning and westbound at night,” Norvell said. “[Drivers] following too closely and not paying attention—rear-end type of accidents.”


Norvell said law enforcement officials are encouraging drivers to avoid the construction zone.


“People are going to have to allow themselves extra time for the next couple of years,” he said.


Potential problems for drivers include being distracted by cellphones, eating food or staring at the construction process, he said. The presence of heavy trucks, machinery and construction workers are also problems for drivers.


Drivers making u-turns and merging to an adjacent lane suddenly at the end of the Westpark Tollway are also activities that could lead to crashes, Norvell said.


“We certainly don’t want [drivers] doing [U-turns] at the end of the Westpark Tollway,” he said.


Meyers said that the project is going to be  a victory for local officials and also a welcome relief for area residents who have been battling congestion for years.


“I’ve been working on this project [for] 10 years. It’s the biggest project I’ve worked on, and it’s also one of the most frustrating,” Meyers said. “I’m going to be happy [when it is done], but I’m not going to be as happy as the people who live there.”

SHARE THIS STORY


MOST RECENT

The Traveling Carrot
Raw vegan food truck The Traveling Carrot finds home in Katy area

The Traveling Carrot’s menu offers a variety of meals made with fruits, vegetables, nuts, seeds and sprouted grains.

The Tessa at Katy is coming soon. (Susan Rovegno/Community Impact Newspaper)
Apartment complex The Tessa at Katy to open spring 2020

Monthly rent at the mulfifamily development begins at $1,135.

District 22 candidates
19 candidates running for US House District 22 file campaign finance reports

In a race with this many candidates, campaign funding can play a major role, especially when it comes to gaining name recognition with voters.

Houston Community College
Houston Community College eyes fall 2020 construction start date for new Katy campus

The new campus will be ready for students and instructors in early 2022.

Early voting begins Feb. 18 in the 2020 Texas primary. (Courtesy Adobe Stock)
Primary Election Guide 2020 Q&A: Get to know Republican candidates for Texas' 9th Congressional District

This year’s Republican primaries include four candidates for Texas' 9th Congressional District.

Handlebar Cyclery
Handlebar Cyclery relocates within Fulshear area

The locally owned store sells bicycles and bike accessories and has a repair shop.

On Feb. 22,  Pedaling the Prairie will host its annual ride, which traverses into Bellville and Katy. (Courtesy Pedaling the Prairie)
To-do list: 15 Katy-area events in February, March 2020

Check out a local community event near you.

Williamsburg Parish
Featured neighborhood: Learn more about Williamsburg Parish in the Katy area

Williamsburg Parish has nearly 900 single-family properties.

The Katy-area Zip codes.
January 2020 real estate data: Median price of homes sold and more in the Katy area

Here is data about the Katy-area residential real estate market across six Zip codes.

Three candidates are running in the Democratic primary for Texas' 10th congressional district. (Courtesy Adobe Stock)
Q&A: Democratic candidates for U.S. representative for District 10 discuss area concerns, immigration policy

Three candidates are running in the Democratic primary for Texas' 10th congressional district.

Waller County 2020 Primary Election Guide: Katy-area polling locations, sample ballot

Early voting runs Feb. 18-28, and election day is March 3.

Back to top