A project in the Avalon Place area will get underway in 2021 under the capital improvement plan approved by Houston City Council on June 24.

The project will move backlot sanitary sewers to the streets, coupled with street reconstruction, drainage, sidewalks, driveways and other improvements throughout the River Oaks area neighborhood.

Houston Public Works will also add bike lanes along Fairview. Advertisement for bids is expected in fall 2020, with construction start in early 2021.

Timeline: fall 2020-23

Cost: $26 million


Funding sources: Dedicated Drainage and Street Renewal Fund, Houston Public Works