Curious as to what new businesses and renovations are underway or coming to the Heights, Montrose and River Oaks area? The following projects have been filed in the last month through the Texas Department of Licensing and Regulation. The following information may be subject to change.

1. PNC Bank: 204 W. 19th St., Houston

Type of work: renovation/alteration

Timeline: Aug. 29-Nov. 30


Estimated cost: $500,000

2. Massage Envy: 1005 Waugh Drive, Houston

Type of work: renovation/alteration

Timeline: Aug. 20-Oct. 15


Estimated cost: $120,000

3. MADabolic: 8200 Washington Ave., Ste. 300, Houston

Type of work: renovation/alteration

Timeline: Sept. 19-Dec. 16


Estimated cost: $195,000

4. Kendall Heaton: 3050 Post Oak Blvd., Ste. 1000, Houston

Type of work: renovation/alteration

Timeline: Sept. 1-Dec. 19


Estimated cost: $200,000

5. Prada: 5085 Westheimer Road, Ste. B2580, Houston

Type of work: renovation/alteration

Timeline: Oct. 17-Dec. 8


Estimated cost: $452,800

6. Oxberry Midtown: 2627 Main St., Houston

Type of work: new construction

Timeline: Dec. 15, 2022-July 1, 2024

Estimated cost: $13 million

7. Jack’s Cafe: 1513 Cambridge St., Ste. N, Houston

Type of work: new construction

Timeline: Jan. 13, 2023-June 15, 2024

Estimated cost: $12.6 million

8. Montrose Blvd.: 3615 Montrose Blvd., Houston

Type of work: new construction

Timeline: Nov. 1, 2022-Feb. 1, 2025

Estimated cost: $130 million

9. Johnnie O’s: 2710-C Drexel, Houston

Type of work: renovation/alteration

Timeline: July 20-Sept. 15

Estimated cost: $135,000

10. Tall Grass: 9 Greenway Plaza, Level 8, Ste. 825, Houston

Type of work: renovation/alteration

Timeline: Sept. 1-Dec. 3

Estimated cost: $366,730